Installation
Sequence of installations are typically carried out as follows:-
- Mark floor for cable access holes using template based on architect final floor plan
- Electrics and data boxes fitted to termination board.
- Frames placed in position in accordance with floor plan and connected side by side.
- Personal power, connectivity modules, and monitor arms installed on slatwall.
- End panels fitted to each bank of desks as per floor plan.
- CPU trolleys placed in position behind access doors.
- Worktops and pedestals installed as per floor plan.