Sequence of installations are typically carried out as follows:-

  • Mark floor for cable access holes using template based on architect final floor plan
  • Electrics and data boxes fitted to termination board.
  • Frames placed in position in accordance with floor plan and connected side by side.
  • Personal power, connectivity modules, and monitor arms installed on slatwall.
  • End panels fitted to each bank of desks as per floor plan.
  • CPU trolleys placed in position behind access doors.
  • Worktops and pedestals installed as per floor plan.